Rockwell Automation 2500 CENTERLINE MCC Joining and Splicing Columns User Manual

Page 22

Advertising
background image

Publication 2500-IN004A-EN-P - August 2009

22 CENTERLINE 2500 Motor Control Centers Installing, Joining and Splicing Columns

Locating the PE Splice Bar

2. Use the PE splice bars to join the horizontal PE of each column

and assemble the splice bars and hardware as shown.

Splicing the PE Conductor

3. Tighten hardware to torque specifications.

See

Torque Requirements for Hardware Connections

on

page 23

.

Do not grease or lubricate hardware.

4. Replace horizontal wireway cover and check that bolts are

secure.

Splice bars are
attached.