22 CENTERLINE 2500 Motor Control Centers Installing, Joining and Splicing Columns
Locating the PE Splice Bar
2. Use the PE splice bars to join the horizontal PE of each column
and assemble the splice bars and hardware as shown.
Splicing the PE Conductor
3. Tighten hardware to torque specifications.
See
Torque Requirements for Hardware Connections
.
Do not grease or lubricate hardware.
4. Replace horizontal wireway cover and check that bolts are
secure.
Splice bars are
attached.