Preface

Before Using This Publication

You can use the tasks described in this publication only after first completing some prerequisite tasks. For example, you
must have your workstations and servers installed and communicating on a network.

Table 1

describes the prerequisites.

The procedures in this quick start use the following software versions:

• RSLogix™ 5000 software, version 20.

x

• FactoryTalk® View software, version 7.0.

IMPORTANT

We suggest that you refer to the PlantPAx Process Automation System Reference Manual, publication

PROCES-RM001

,

for system guidelines during and after you use this guide. For example, the reference manual documents recommended task
configurations applied by the procedures contained within this guide. There also are recommended rules to follow when creating
your specific configuration after completing this quick start.

Table 1 - Required Tasks to Complete before Using This Quick Start

Objective

Task Descriptions

Define the system

• Collect requirements. For example, I/O counts,

redundancy, simplex controllers, and so forth

• Choose the controller family, I/O family, network

topology. For example, EtherNet/IP, Ring or Star,
ControlLogix®, CompactLogix™

• Size your system based on requirements
• Create system layout by assigning slots and

IP addresses, chassis locations, I/O counts, and so forth

IMPORTANT: The system must be defined and sized
properly by using the PSE (shown at right) that is part of
the IAB tool. The worksheet that is included with this
guide (see

page 69

) cannot determine sizing

requirements but is a helpful tool for defining information
that you need for template initiation. To size a system, use
the PSE.

Install the system

• Set up infrastructure. For example, install computer

hardware, wire networks, configure network switches

• Install servers and workstations (PASS, OWS, EWS)

If using virtual image templates, see the Virtual Image
Templates User Manual, publication

9528-UM001

or
Configure the operating system and NIC cards, join a
domain, and install software

• Set up the FactoryTalk Directory (FTD) server
• Install controller hardware (chassis, power supply,

modules)

• Test communication. For example, ping or use RSWho

to locate each server, workstation, and controller

IMPORTANT: The FTD location must be specified for each
workstation and server on your system.

46249

OWS

PASS Server

EWS

IMPORTANT

It’s possible to follow the tasks in this quick start without the entire production environment. However, a minimal set up is
required, including PASS servers and controllers.