OPERATION

2. Plasma Gas Pressure Regulator/Filter Assembly

Pressure Regulator to adjust the plasma input gas
pressure to the Power Supply. The Pressure Regu-
lator has a built-in air line filter.

A-02110

3

5

1

4

2

Figure 4-4 Rear Panel

3. Secondary Gas Pressure Regulator/Filter Assem-

bly

Pressure Regulator to adjust the secondary input
gas pressure to the Power Supply. The Pressure
Regulator has a built-in air line filter.

4. Coolant Reservoir

The coolant reservoir supplies the system with
coolant to cool the torch and torch parts during
operation. The maximum capacity of the reser-
voir is two gallons of coolant.

Inside the reservoir, in the filler hole, is a basket
and deionizer bag. The bag removes charged par-
ticles from the coolant after it is returned to the
reservoir and prevents the coolant from becom-
ing conductive. If the coolant becomes conduc-
tive it must be replaced (see NOTE).

NOTE

Refer to Section 5.02, General Maintenance, sub-
sections 'E' and 'F' for procedures on checking and
replacing coolant.

5. Gas Input

Input connections for plasma and secondary gases.
Acceptable gases are as follows:

Plasma Gases - Air, Nitrogen, Argon Hydrogen

Secondary Gases - Air, Nitrogen, Carbon Dioxide

WARNING

This unit not to be used with oxygen (O

2

).

6. Optional Two Stage Air Line Filter

The optional filter will remove moisture and con-
taminants from the air stream when using com-
pressed air. The filter is capable of filtering to at
least 5 microns.

A-02082

5

2

3

4

1

6

Figure 4-5 Rear Panel With Optional Two Stage

Filter

4.03 Sequence of Operation

The following is a typical sequence of operation for this
cutting system. Refer to Appendix 2 for a block diagram.

1. Close main power source disconnect.

a. AC power is available at the Power Supply.

2. Place RUN/SET switch to RUN mode.

Advertising