07 check main input rectifier, Check main input rectifier -6, Transarc 130i – Tweco 130i Transarc Service Manual User Manual

Page 48: 08 check main input rectifier

Advertising
background image

TROUBLESHOOTING 6-6 Manual 0-5282

TRANSARC 130i

IGBT Testing

Multimeter Lead Placement

Ohms

IGBT V8 & V8-1

Positive meter lead to testpoint 4

Negative meter lead to testpoint 3

>150 Ω

IGBT T1 & T2

Positive meter lead to testpoint 6

Negative meter lead to testpoint 5

>150 Ω

IGBT T4 & T5

Positive meter lead to testpoint 8

Negative meter lead to testpoint 7

>150 Ω

Table 6-4: IGBT’s, Multimeter set to measure ohms (Ω)

Inrush Resistor

Multimeter Lead Placement

Ohms

Resistor

Positive meter lead to testpoint 9

Negative meter lead to testpoint 10

4 Ω

Table 6-5: Inrush PTC, Multimeter set to measure ohms (Ω)

DIODE Testing

Multimeter Lead Placement

Ohms

DIODE V7

Positive meter lead to testpoint 11

Negative meter lead to testpoint 12

0.2 – 0.8 VDC

DIODE T14, T15

Positive meter lead to testpoint 13

Negative meter lead to testpoint 14

0.2 – 0.8 VDC

DIODE T16, T17

Positive meter lead to testpoint 15

Negative meter lead to testpoint 16

0.2 – 0.8 VDC

Table 6-6: Diodes, Multimeter set to measure Diode Voltage

6.08 Check main input rectifier

A-11846