Install Primary Seed Hoses

Primary seed hose is 2

1

2

inches (6.4cm) in diameter and

is delivered in 100-foot (30m) rolls:

990-125R SEED HOSE 2 1/2 ID KANAFLEX

Cut primary hoses to connect each meter-box outlet on
the cart with a distribution tower on the implement.

Refer to Figure 39 and Figure 40

61. From 1 to 4 (NTA3010) or to 5 (NTA3510), number

the open ports at the back of the meter from left to
right, skipping any capped meter ports.

Note: Do not move caps. Meter shaft under a cap has

fillers, not flutes, and cannot meter material.

Start with Tower 3.

62. Measure the expected hose length and mark

hose

with grease pencil or tape.

63. Route hoses over implement frame as shown in

Figure 37 (NTA3010) or
Figure 38 (NTA3510) on page 28.

Run hoses under fold cylinders, under top frame
tubes, above lower frame tubes, and through hose
holders along the routing.

Note: Do not run hoses above top tubes, or the hoses

may be too short, and they will interfere with any lat-
er weight installation.

Refer to Figure 39

64. Select one:

800-180C 2 1/2 AIR HOSE BAND CLAMP

Slide band clamp

over implement end of

hose

, then slide hose at least two inches onto

tower inlet

. Allow enough hose slack so that

implement raising, lowering, folding and unfolding
will not pinch or bind hose.

65. Using a hacksaw, cut hose so it slides at least two

inches onto meter outlet.

66. Select one:

800-180C 2 1/2 AIR HOSE BAND CLAMP

Slide band clamp

over cart end of hose, then

slide hose onto meter outlet. Install clamp so it does
not interfere with other hoses, clamps, doors or
meter-door handles.

67. Repeat step 62 through step 66 for Towers 2, 4, 1

and 5.

68. Secure all hoses onto the frame using the provided

cable ties. Be sure hoses will not be damaged by
folding, unfolding, raising, lowering any later weight
installation.

IMPORTANT !

Do not cut hose until routed over implement. Lengths
in table are approximate. Actual lengths may vary
from implement to implement.

IMPORTANT !

Connect each tower to its corresponding outlet on the
cart. For example, connect the second tower from the
left to the second meter outlet from the left. For exam-
ple, for NTA3010 and ADC2220, do not connect a
seed hose to the center meter outlet.

Figure 39

Primary Hose at Tower

16282

62

35

31

62

62

Figure 40

Meter Outlets

14467
26302

35

35

35

ADC2220

ADC2350

35

35

62

31

35

35

Advertising
This manual is related to the following products: