20°F 25°F 30°F 35°F

SIZE

flow

H/L

flow

H/L

flow

H/L

flow

H/L

gpm feet gpm feet gpm feet gpm feet

500

43 1.7 34 1.1 28 0.9 24 0.7

750

64 3.3 51 2.3 43 1.7 36 1.2

1000

85 5.0 68 3.6 57 3.1 49 2.2

1250

106 8.1 85 6.1 71 4.7 61 3.4

1500

128 10.0 102 7.2 85 5.5 73 4.2

1750

N/R N/R 119 10.5 99 8.4 85 5.8

2000

N/R N/R 136 12.5 113 10.4 97 8.3

Metric Equivalent

11°C 14°C 17°C 19°C

SIZE

flow

H/L

flow

H/L

flow

H/L

flow

H/L

lpm m lpm m lpm m lpm m

500 161 0.5 129 0.3 107 0.3 92 0.2

750 241 1.0 193 0.7 161 0.5 138 0.4

1000 321 1.5 257 1.1 214 0.9 184 0.7

1250 401 2.5 322 1.9 269 1.4 231 1.0

1500 483 3.0 386 2.2 322 1.7 276 1.3

1750

N/R N/R 451 3.2 375 2.6 322 1.8

2000 N/R N/R 515 3.8 429 3.2 368 2.5

Notes: gpm = gallons per minute, lpm = liters per minute,

H/L = headloss, ft = headloss in feet, m = headloss in meters.

Maximum temperature rise is 35°F (19°C), as shown.

Headloss is for boiler’s heat exchanger only.

N/R = not recommended.

Table 8. Water Flow Requirements - PNCH.

SECTION 4A.

Water Connections —

Pennant Boiler

4A.1 Heating System Piping:

Hot Supply Connections — Boiler

NOTE: This appliance must be installed in a closed

pressure system with a minimum of 12 psi (82.7kPa)

static pressure at the boiler.

Hot water piping should be supported by suitable

hangers or floor stands. Do not support piping with

this appliance. Due to expansion and contraction of

copper pipe, consideration should be given to the type

of hangers used. Rigid hangers may transmit noise

through the system resulting from the piping sliding in

the hangers. It is recommended that padding be used

when rigid hangers are installed. Maintain 1" clearance

to combustibles for hot water pipes.

Pipe the discharge of the relief valve (full size)

to a drain or in a manner to prevent injury in the event

of pressure relief. Install an air purger, an air vent,

a diaphragm-type expansion tank, and a hydronic

flow check in the system supply loop. Minimum fill

pressure must be 12psig (82.7kPa). Install shutoff

valves where required by code.

Suggested piping diagrams are shown in

Figures

4 through 8.

These diagrams are meant only as a guide.

Components required by local codes must be properly

installed.

Note the recommended location of the

temperature sensor on the diagrams; you must provide

a location for the additional sensor shipped with the

Pennant. This sensor may be strapped onto pipe from

1" to 4" diameter, or inserted into an immersion well.

4A.2 Cold Water Make-Up — Boiler

1. Connect the cold water supply to the inlet

connection of an automatic fill valve.

2. Install a suitable back flow preventer between the

automatic fill valve and the cold water supply.

3. Install shut off valves where required.

NOTE: The boiler, when used in connection with a

refrigeration system, must be installed so the chilled

medium is piped in parallel with the boiler with

appropriate valves to prevent the chilled medium from

entering the boiler.

The boiler piping system of a hot water heating

boiler connected to heating coils located in air

handling appliances where they may be exposed to

refrigerated air circulation must be equipped with flow

control valves or other automatic means to prevent

gravity circulation of the boiler water during the

cooling cycle.

A boiler installed above radiation level, or as

required by the authority having jurisdiction, must be

provided with a low water cutoff device either as a part

of the boiler or at the time of boiler installation.

4A.3 Water Flow Requirements — Boiler

A hydronic heating (closed loop) application

re-circulates the same fluid in the piping system. As a

result, no new minerals or oxygen is introduced into

the system. To ensure a proper operating temperature

leading to long boiler life, a flow rate has been

established based on the fluid temperature rise for this

specific size boiler.

Pump-mounted boilers can be ordered for use in

primary secondary piping systems. The pumps used

are sized for the headloss through the heater, plus 30

feet (9.1m) of full-sized piping (same size as boiler

outlet) and a normal number of fittings.

Table 8

specifies water flow rates for boilers,

which will enable the user to size a pump. The

headloss shown is for the heater only, and the user

will need to add the headloss of the system piping to

properly size the pump.

The minimum inlet water temperature for the

Pennant is 120°F (49°C) to avoid condensing on the

copper coils.