LEGEND

CHECK VALVE

THERMOMETER

TEMPERATURE
SENSOR

GLOBE VALVE

EXPANSION TANK
WITH AIR SCOOP AND

AUTO AIR VENT

3-WAY VALVE

VALVE

PRESSURE REDUCING VALVE
W/ FAST FILL BYPASS

PURGE

VALVE

PUMP

CAUTION: THIS DRAWING SHOWS SUGGESTED
PIPING CONFIGURATION AND VALVING, CHECK
WITH LOCAL CODES AND ORDINANCES FOR
ADDITIONAL REQUIREMENTS.

PRIMARY/SECONDARY MANDITORY FOR ALL
VARIABLE FLOW SYSTEMS

INSTALL AIR VENTS AT HIGH POINTS IN SYSTEM

PIPING & SIZING OF EXPANSION TANK
PER TANK MANUFACTURER'S INSTRUCTIONS

DIMENSION "C" (COMMON PIPING) TO BE FOUR
PIPE DIAMETERS, MAX. (NO ELBOWS OR VALVES)

BOILER CIRCUIT PIPING MUST BE EQUAL
TO BOILER WATER CONNECTION SIZE

BOILER CIRC. PUMP SIZED FOR FLOW THROUGH BOILER

DOTTED DEVICES INDICATE ALTERNATE LOCATIONS

PUT BOILER CONTROL SENSOR IN THE SYSTEM

PUMP LOCATION FOR PUMP-MOUNTED UNITS

SUPPLY WHEN USING THIS PIPING STYLE.

MINIMUM BOILER INLET WATER TEMPERATURE
MUST BE AT LEAST 120°F.

C

SYSTEM PUMP

MAKE-UP

COLD WATER

SUPPLY

SYSTEM

PUMP LOCATION FOR
NON-PUMP-MOUNTED UNITS

RETURN

SYSTEM

T1

T1

A

B

A

B

ADJUSTMENT PROCEDURE TO MAINTAIN
120°F INLET TEMP:
1. Turn on boiler and open valves A & B.
2. After steady-state operation, if T1 is less than

120°F, slowly close valve B until T1 climbs to
120°F.

3. If T1 is greater than 120°F, slowly close valve

A until T1 drops to 120°F.

4. Check after system operating temperature has

stabilized. Make final adjustments.

Figure 8. Hydronic Piping - Primary-Secondary, Reverse-Return, Low Temperature.