OPERATING INSTRuCTIONS

6.1 Filling the Boiler System

1. Ensure the system is fully connected. Close all

bleeding devices and open make-up water valve.

Allow system to fill slowly.

2. If make-up water pump is employed, adjust

pressure switch on pumping system to provide

a minimum of 12 psi (81.8 kPa) at the highest

point in the heating loop.

3. If a water pressure regulator is provided on the

make-up water line, adjust the pressure regulator

to provide at least 12 psi (81.8 kPa) at the highest

point in the heating loop.

4. Open bleeding devices on all radiation units

at the high points in the piping throughout

the system, unless automatic air bleeders are

provided at such points.

Note that there is an air bleed (coin vent)

located in the back of the unit, on top of the

flue collector, to bleed air from the secondary

(stainless steel) heat exchanger.

5. Run system circulating pump for a minimum of

30 minutes with the boiler shut off.

6. Open all strainers in the circulating system,

check flow switch operation, and check for

debris. If debris is present, clean out to ensure

proper circulation.

7. Recheck all air bleeders as described in Step 4.

8. Check liquid level in expansion tank. With the

system full of water and under normal operating

pressure, the level of water in the expansion tank

should not exceed ¼ of the total, with the balance

filled with air.

9. Start up boiler according the procedure in this

manual. Operate the entire system, including the

pump, boiler, and radiation units for one (1) hour.

10. Recheck the water level in the expansion tank. If

the water level exceeds ¼ of the volume of the

expansion tank, open the tank drain, and drain to

that level.

11. Shut down the entire system and vent all

radiation units and high points in the system

piping, as described in Step 4.

12. Close make-up water valve and check strainer in

pressure reducing valve for sediment or debris

from the make-up water line. Reopen make-up

water valve.

13. Check gauge for correct water pressure and also

check water level in the system. If the height

indicated above the boiler insures that water is at

the highest point in the circulating loop, then the

system is ready for operation.

14. Refer to local codes and the make-up water

valve manufacturer’s instructions as to whether

the make-up water valve should be left open or

closed.

15. After placing the unit in operation, the ignition

system safety shutoff device must be tested. First,

shut off the manual gas valve, and call the unit

for heat. Main gas terminals will be energized,

attempting to light, for seven (7) seconds, and

then will de-energize. The unit will go into

lockout mode. Second, turn the power off, press

the manual reset button on the ignition control,

open the manual gas valve and allow the unit

to light. While the unit is operating, close the

manual gas valve and ensure that power to the

main gas valve has been cut.

16. Within three (3) days of start-up, recheck all air

bleeders and the expansion tank as described in

Steps 4 and 8 above.

Important: The installer is responsible for

identifying to the owner/operator the location of all

emergency shutoff devices.

WARNING

Do not use this appliance if any part has been

under water. Immediately call a qualified service

technician to inspect the appliance

and to replace any part of the control system and

any gas control that may have been

under water.

6.2 Operating the Burner and Set up

The Rheos+ modulating appliance utilizes an

advanced, state-of-the-art design. The setup must be

checked before the unit is put in operation. Problems

such as failure to start, rough ignition, strong exhaust

odors, etc. can be due to improper setup. Damage to

the boiler resulting from improper setup is not covered

by the limited warranty.

REQUIRED TOOLS:

Differential pressure gauge capable of reading

negative 0.01 inches W.C. (0.002kPa).

1. Using this manual, make sure the installation

is complete and fully in compliance with the

instructions.

2. Determine that the appliance and system are

filled with water and all air has been bled from

both. Open all valves.

3. Observe all warnings on the Operating

Instructions label and turn on gas and electrical

power to appliance.

4. There is a gas/air test panel to the left of the

control panel, at the front of the unit (see Figures

25 and 32). Ensure that all four valves on the test

panel are closed (see Figure 26).