Prior to use – VACUUBRAND DCP 3000 User Manual

Page 31

Advertising
background image

page 31 of 64

Prior to use

➨

Connect the VSK 3000 or VSP 3000 gauge head by its connecting

cable (VACUU•BUS line) to a jack at the rear side of the DCP 3000.

➨

Connect the gauge head to the vacuum chamber via either the small

flange connection, the hose nozzle, or PTFE tubing. Avoid contamina-

tion (oil/oil mist) of the gauge head when generating the vacuum with

an oil-sealed vacuum pump.

+

Do not position the gauge head directly at the inlet of an oil-sealed

pump. The diameter of the connecting tubing should be as large as

possible.

+

Inside a vacuum system where evaporation occurs, e.g., a rotary

evaporator, the vacuum is not uniform. For example, a condenser can

act as a pump, or the vacuum in the connecting tubing can be higher

or lower than in the application itself. This affects the measurement re-

sults. Therefore, carefully choose the position at which to connect the

pressure transducer.

+

Condensate and deposits will affect the measurement results.

+

If residues occur or when working with aggressive or condensable

substances, install a gas washing bottle in front of the pressure trans-

ducer.

+

Position the pressure transducer in such a way that condensate

cannot flow towards it.

VSP 3000:

Recommended orientation: Vertically with vacuum connection pointing

downwards. If mounting the VSP 3000 in any other orientation, a read-

justment is recommended (see section “Readjustment of VSP 3000”, pg.

56).

+

If necessary, clean the gauge head.

➨

Switch the equipment on.

Advertising