11 Electrical Connection

ELECTRICAL

CARTRIDGE

FIXING

SCREWS

Diagram 11.3

11.3 Electrical Cartridge Securing

Close the cartridge and secure with the previously removed

screw.

Push the electrical cartridge into the interface housing on

completion of the wiring, see diagram 11.3.

Secure with the two cartridge retaining screws provided in the

cartridge body.

11.4 Electrical Connections - Testing

Carry out preliminary electrical system checks as below:

1. Test insulation resistance to earth of mains cables.

2. Test the earth continuity and short circuit of cables.

3. Test the polarity of the mains.

NOTE: If you require to test the appliance refer to section 14.

12 Commissioning

IMPORTANT: At the time of commissioning, complete all

relevant sections of the Benchmark Checklist located in the

centre pages of this document.

12.1 Preliminaries - All Systems

DO NOT operate the boiler without water.

The commissioning should be carried out by a

competent

person approved at the time by the Health and Safety

Executive in accordance with the current issue of BS6798.

Make sure that the system has been thoroughly flushed

out with cold water and that all cleanser, if used, has been

removed.

With the gas service isolation valve closed, with no demand

from any external controls and the power supply to the boiler

switched off, test for gas soundness and purge air from the

gas supply.

12.2 Filling the Heating Circuit

With the gas service isolation valve closed and with no

demand from any external controls.

1. Fill the heating system.

Sealed system only - fill the system to a pressure of

1.0bar.

2. Vent all air from the system - repeat as

neccessary until the system is full and all the air has

been vented.

12.3 Gas Supply

The gas valve is factory set for natural gas (G20) and should

need no adjustment. Turn on the gas supply at the isolation

valve, see diagram 12.1. Check the supply pressure at the

pressure test point is 20mbar.

Diagram 12.1

14507

GAS SERVICE

ISOLATION

VALVE

GAS SUPPLY

PIPE IN

PRESSURE

TEST POINT