12 Commissioning

Commissioning should only be carried out by a

competent

person approved at the time by the Health and Safety

Executive.

12.4 Initial Lighting

NOTE: The combustion for this appliance has been

checked, adjusted and preset at the factory for operation

on natural gas (G20) as defined on the appliance data

label.

Do not adjust the Gas/Air ratio valve.

No measurement of the combustion is necessary, having

checked :

● the appliance has been installed in accordance with the

instructions.

● the integrity of the flue system and flue seals.

● that all internal/external controls are calling for heat.

● the gas service isolation valve, diagram 12.1, is open.

DO NOT operate the boiler without water.

The lighting procedure of the boiler is fully automated.

Refer to diagram 12.2.

● With no demand from any external controls, switch on the

electrical supply to the boiler.

● Open the gas service isolation valve, see diagram 12.1.

● The appliance will enter a self checking routine then the

fan should start and the ignition will commence.

The boiler, if necessary, will automatically repeat the

ignition sequence a further 4 times.

● If the burner fails to ignite “F1” will be displayed, initially,

this may be due to air in the gas supply line.

● Once the system has been purged of air. Press and

hold the “ Mode “ button of the boiler user controls for 2
seconds, the Central Heating symbol,

will flash. Use the

“SELECTOR” buttons to adjust CH temperature.

Diagram 12.2

14513

After 10 seconds of inactivity the display will reset to indicate

the water temperature.

● Turn ON your external controls and select the room

temperature required.

The boiler will operate automatically.

NOTE: The display will indicate the Heating system water

temperature or a fault code if in a fault condition.

12.5 Check the Gas Inlet Pressure & Gas

Rate

The supply from the governed meter must be of adequate

size to provide a steady inlet working pressure of 20mbar (8in

wg) at the boiler. On completion, test the gas installation for

tightness using the pressure drop method and suitable leak

detection fluid, purge as necessary.

NOTE: Due to the modulating operation of the boiler and

the need to check the gas inlet pressure and measure the

gas rate at maximum rate, it will be necessary to force it to

maximum.

Press the “reset” button on the controls fascia, release

and immediately press and hold in the “+” button. After

approximately 5 seconds “Hi” will be displayed. Pressing

the mode button when “Hi” is selected will force the boiler

to maximum rate, the display will flash between “Hi” and the

“default display” this will indicate the boiler has been forced to

maximum.

Operational Gas Inlet Pressure

With ALL other gas appliances operating, check the

operational supply pressure at the gas service isolation valve

test point, see diagram 12.1.

The nominal supply pressure for Natural Gas (G20) is 20mbar.

Turn the taps and appliances off, then disconnect the pressure

gauge.