Protection systems, Commissioning, start-up, operation and shutdown, Pre-commissioning procedure – Flowserve IDP CPXV User Manual

Page 16: Pre-commissioning (5.1)

Advertising
background image

CPXV and CPXRV USER INSTRUCTIONS ENGLISH 71569193 09-14

Page 16 of 48

flowserve.com

4.7 Protection systems

The following protection systems are

recommended but are mandatory if the pump is
installed in a potentially explosive area or is handling
a hazardous liquid. If in any doubt consult Flowserve.

If there is any possibility of the system allowing the
pump to run against a closed valve or below
minimum continuous safe flow a protection device
must be installed to ensure the temperature of the
liquid does not rise to an unsafe level.

If leakage of product from the pump or its associated
sealing system can cause a hazard it is recommended
that an appropriate leakage detection system is installed.

To prevent thrust bearing damage becoming a safety
hazard it is recommended that monitoring of vibration
is carried out.

Where there is the potential hazard of a loss of a seal
barrier fluid the barrier fluid sustem must be monitored.

Where there is a risk that the external flush to a seal or
bearing could fail, for example by freezing, blocking by
debris or loss of supply pressure, then the flow must be
monitored.

Where there is product flush via filters then flow must
be monitored.

Visual indicators are suitable when equipment is
regularly inspected, but sensors connected to the pump
control system must be used if the pump runs remotely.

For Category 2 equipment the monitoring must create
an alarm to the plant operator or shut down the pump.

For equipment to category 1/2 or 1/3 with external flush
or filtered product flush, the flow to each line bearing
must be separately monitored and temperature sensors
fitted on each line bearing that is connected to the
pump control system. The monitoring equipment must
be suitable for the hazardous area.

For equipment to category 1/2 or 1/3 the presence of
seal barrier liquid and the temperature of the inboard
seal must both be monitored and connected to the
pump control to create an alarm signal to operators, or
to shut down the pump.

See also sections 5.8.2 to 5.8.7.

The protection sensors will generally be fitted by
Flowserve, but the connection to the pump control
system will often be by the installer of the pump.
Installers must ensure that the instructions of the
sensor manufacturer are followed, that any additional
components are suitable for the zone in which they
are to be installed, and that their trip levels are set
and checked during commissioning. The protective
systems must also be periodically checked in
accordance with the sensor manufacturer’s
instructions or with local site standards.

When clean process liquids are used to flush
bearings the user must periodically check that there
is no contamination entering the sump.

5

COMMISSIONING, START-UP,

OPERATION AND SHUTDOWN

These operations must be carried

out by fully qualified personnel.

Contact the factory for recommendations for

operation with pumpage of any fluid other than what the
pump was specfiically designed for.

5.1 Pre-commissioning procedure


Prior to starting the pump it is essential that the
following checks be made.



Motor properly secured to the motor stool



All fasteners tight and to the correct torque



Coupling guard is in place



Rotation check, see section 5.4.



Impeller clearance setting



Shaft seal properly installed



Seal support system operational



Bearing lubrication



Pump instrumentation is operational



Rotation of shaft is free when pump mechanically

and electrically isolated

5.1.1 Rolling element bearing lubrication
Determine the mode of lubrication of the pump set, e.g.
grease, oil, product lubrication, external clean liquid etc.

For oil lubricated pumps, fill the bearing

housing with correct grade of oil to the correct level.

Advertising
This manual is related to the following products: