3 switching on the sunny string-monitor – SMA SSM8-21-BS User Manual

Page 40

Advertising
background image

7  Commissioning

SMA Solar Technology AG

40

SSMxx-21-IA-BS-JP-en-20

Installation Manual

7.2.3 Noting Down the Serial Number of the String-Monitor Unit

The serial number clearly identifies the String-Monitor Unit. The serial number can be found on the type label at the bottom

right-hand corner of the String-Monitor Unit.
You will need the serial numbers for detecting the String-Monitor Units. All serial numbers of the String-Monitor Units must

be noted in the commissioning report.

Figure 17: Position of the serial number on the String-Monitor Unit

Procedure:

• Identify the serial numbers of the String-Monitor Units and note them in the commissioning report.

7.3 Switching On the Sunny String-Monitor

Requirement:

☐ The String-Monitor Unit is supplied with voltage.

Procedure:

1. Open the fuse holders.

3. Close the fuse holders.
4. Switch on the DC load-break switch.

Position

Designation

A

Serial number of the String-Monitor Unit

:$51,1*

Fire risk caused by incorrect rating of string fuses or by use of incorrect string fuses

• Ensure that the rating of the string fuses is correct.
• Only install string fuses supplied or approved by SMA Solar Technology AG for Sunny String-Monitors.

2.

'$1*(5

Danger to life due to electric shock if live components of the Sunny String-Monitor are touched

• Only insert the string fuses in the Sunny String-Monitor when the power is switched off.

Advertising