3 installation – GE 225 User Manual

Page 10

Advertising
background image

g

GE

OPM_SGS_ISG_M22_M30_0US_V011.doc

10/38 Installation

Guide

SG Series 225 & 300 kVA

3 INSTALLATION

3.1 TRANSPORT

Transport UPS only in upright position!

The UPS is packaged on a pallet suitable for
handling with a forklift.

Pay attention to the center of gravity.

The UPS must be moved in upright position.
Do not tilt cabinets more than +/- 10° during
handling.

Move the UPS in it’s original package to the
final destination site.

Do not stack other packages on top:
This could damage the UPS.

If the UPS must be lifted by crane, use suitable
lifting straps and spreader bars.
Note of the center of gravity marked on the
package.

Forklift

Crane

Fig. 3.1-1 UPS cabinets moving

Check for sufficient floor and
elevator loading capacity.

3.1.1 Dimensions

and

weight

Dimensions

SG Series 225 and 300 kVA

(W x D x H)

64.96 x 31.50 x 70.90 inches

1,650 x 800 x 1,800 mm

S

G

S

_225

-30

0_U

P

S

d

im

ens

ions

_GE

_0

1US

H

W

D

Fig. 3.1.1-1 UPS cabinet dimensions

Weight

SG Series 225 and 300 kVA

UPS rating

Weight

lbs / kg

Floor loading

lbs/sq.ft - kg/m

2

SG Series 225 kVA

2,756 / 1,250

194 / 947

SG Series 300 kVA

3,087 / 1,400

218 / 1,061

P.S.: Weights including the 5th harmonic filter.