3.7.3 Battery over current protection and wire sizing

Please read the safety precautions at the front of this guide carefully, and thoroughly
review the Battery manufacturers installation and maintenance manual before connecting
the batteries to the UPS.

If the UPS system has been purchased with an accompanying Battery Cabinet, that
cabinet should have an integral Battery Circuit Breaker.
If the UPS has been purchased without a Battery Cabinet or remote rack mounted
batteries are to be used then DC over current protection must be provided by others.

Choose an appropriate DC fuse or circuit breaker using the current data in the chart
below.

Minimum Battery Cable requirement is based on the current data below.

The AC values below are current ratings per phase.

These maximum and nominal ratings should be considered when choosing the

appropriate AC over current protection device.

NEC (National Electric Code) Section 210-20 a rules must be applied.

DC current rating is the maximum battery discharge current which the UPS allows.

(See Fig. 3.7.1-1 and 3.7.1.2)

AC Input

Rectifier

AC Input

Bypass

AC Input

DC Input

F1

F3

Nom. Max.

F2

Nom. Max.

F4

SG Series 225 kVA

301 A

360 A

271 A

301 A

360 A

401 A

SG Series 300 kVA

401 A

480 A

361 A

401 A

480 A

535 A

Size of Branch Circuit Over current Protection - All Models: - "CAUTION - To reduce

the risk of fire, only connect UPS to a circuit provided with (See below) maximum

amperes branch circuit over current protection in accordance

with the NEC (National Electric Code), NSI / NFPA 70

AC Input

Rectifier

AC Input

Bypass

AC Input

DC Input

F1

F2

F3

F4

SG Series 225 kVA

450 A

350 A

450 A

600 A

SG Series 300 kVA

600 A

500 A

600 A

700 A

WIRING
Wire sizing according to
NEC Section 210-20 (a) Table 310-16
Use 75°C (167°C) copper wire

Wiring requirements:
AC INPUT RECTIFIER:

3-Phase, 3 wire plus Ground

AC INPUT BYPASS:

3-Phase, 4 wire plus Ground

AC OUTPUT:

3-Phase, 4 wire plus Ground

DC INPUT:

2 wire (positive and negative) plus Ground

Maximum cable diameter that compression lugs can accept.
Refer to torque specifications table for torque requirements.

Rectifier Input Bypass Input

DC Input

AC Output

GND

SG Series 225 kVA

2 x 500 kcmil 2 x 500 kcmil 2 x 750 kcmil 2 x 500 kcmil

350 kcmil

SG Series 300 kVA

2 x 750 kcmil 2 x 500 kcmil 2 x 750 kcmil 2 x 500 kcmil