1 procedures for single sg series 400 & 500, 1 start-up of the sg series 400 & 500, Procedures for single sg series 400 & 500 – GE Industrial Solutions SG Series 400 & 500 Operating Manual User Manual

Page 45: Start-up of the sg series 400 & 500, Open the front door and make sure that, The safety screens are fixed in their position, Leds on synoptic diagram, Continue, Overall test results

Advertising
background image

Modifications reserved

Page 45/79

OPM_SGS_USM_M40_M50_2US_V010.doc

User Manual SG Series 400 & 500 UL S2

7.1 PROCEDURES FOR SINGLE SG Series 400 & 500

7.1.1 Start-up of the SG Series 400 & 500

WARNING !

Before proceeding to Turn ON the UPS System, ensure that the AC and DC external
isolators are OFF (Pos. O), and prevent their inadverted operation.
Ensure that the output load distribution can be powered and all the output isolators
are open (Pos. O).

Open the front door and make sure that:

All the connections to the input/output bus bars of the UPS have been made correctly.

The safety screens are fixed in their position.

The UPS Output Switch Q1, Manual Bypass Switch Q2 (option) and the External Battery Switch or
Fuses
must be open (Pos. O).

LEDs on Synoptic Diagram

S

G

S

_4

00-

5

00_

S

2_

S

w

itc

h

es

Q

1-

Q

2_01

Q1

0 OFF

I ON

Q2

0 OFF

I O

N

Q1

UPS Output switch

Q2

Manual Bypass switch (option)

LED 1

Utility Rectifier OK

LED 2

Utility Bypass OK

LED 3

Rectifier ON

LED 4a Discharging Battery
LED 4b Charging Battery

LED 5

Inverter available

LED 6

Inverter ON

LED 7

Q1 closed

LED 8

Automatic Bypass ON

LED 9

Manual Bypass Q2 ON (option)

LED 10

Load on UPS

Key Key Key LED LED LED

Inverter ON

Inverter OFF

Load Off

Stop Operation

Alarm

Operation


1. Switch-ON the Utility Voltage from the input distribution (both rectifier and bypass if

separated).

At this stage the electronic power supply is switched ON.

Overall test results

Test1 OK

Test7 OK

Test2 OK

Test8 OK

Test3 OK

Test9 OK

Test4 OK

Test10 OK

Test5 OK

Test11 OK

Test6 OK

The UPS performs a SELFTEST.

A successful termination of the tests will be indicated with
Overall test results “OK”.

Commissioning cannot be continued should one or more tests

result to be negative.

Please contact in this case your Service Center.

With “Overall test results - OK” the Synoptic Diagram is displayed.
LED 1 (Utility Rectifier OK) and LED 2 (Utility Bypass OK) must be ON.
The buzzer sounds, press the “MUTE” key to reset acoustical alarm. LED Alarm remains lit.

Continue