7.2.7 Restore to normal operation after “Load Off”

NOTE !

Make sure the all Units of the Parallel System to be status of the activation of “Load
Off”
, i. e. UPS Output Switches Q1 closed (Pos. I), Manual Bypass Switches Q2 (option)
open (Pos. O) and External Battery Switch or Fuses
connected (Pos. I).
If eBoost™
option is available, make sure that eBoost™ Operation Mode is disabled
before starting the shutdown procedure.




View of the synoptic diagram, on all UPS units, after
pressing the
Load Off” key.
All Contactors are open.
Rectifier, Inverter and Static-Switch shutdown.
LED Alarm is lit.




`

Home\Commands

COMMANDS

RESET TOTAL OFF

REQUEST

TOTAL

OFF

V



1. Reset “Load Off” of the Parallel System.

Restore the command “Load Off”, on anyone of the
Parallel Units, by entering the screen:
COMMANDS / RESET TOTAL OFF

• The Load is supplied by the Utility through the

Automatic Bypass of all Units.

Rectifiers start automatically, blinking LED 3 (Rectifier

ON) indicates Soft-start.

• At the end of Rectifier Soft-start, the LED 3 (Rectifier ON)

remains lit.

LED Alarm is lit.

The Synoptic Diagram, on all UPS units, must display the statusLOAD SUPPLIED BY AUTOMATIC BYPASS.