6.2.3 Layout of control PCB inside control box

Fig. 53 Control box inside (w/o SEL unit)

Slot Control board

Z-No.

Orientation

1

-

-

-

2

NEKO unit (ED trip)

128 750 R1

equipment to left

3

Voltage converter

128 730 R2-R4 equipment to left

4

SU-control unit

128 700

equipment to right

5

-

-

-

6

ST/UVR control unit

128 710 R1, R2

equipment to left

Table 5 Layout of control PCBs inside the box w/o SEL


Fig. 54 Control box inside (with SEL unit)

Slot Control board

Z-No.

Orientation

1

NEKO unit (ED trip)

128 750 R1

equipment to right

2

Voltage converter

128 730 R2-R4 equipment to right

3

SU-control unit

128 700

equipment to left

4

ST/UVR control unit

128 710 R1, R2

equipment to right

5

-

-

-

6

SEL control unit

128 785 R1-R2

equipment to left

Table 6 Layout of control PCBs inside the box with SEL


Warning: The isolation plates between the control
boards and at the wall of the box must always be

present!

Hint: In older systems, the control boards may be
installed turned 180 °!

6.2.4 Replacement of the control boards

1. OPEN the breaker.
2. Disconnect power supply, and pull out all
the plugs from control box’s terminals.
3. If a NEKO control unit is installed, wait 1
minute until capacitors discharge.

Fig. 55-1 Unscrew and remove all the external plugs

Fig. 55-2 Unscrew four bolts of the box cover

Fig. 55-3 Carefully lower the box cover

Slot numbers:
1

2

3 4 5 6

Slot numbers:
1

2

3 4 5 6