GE Industrial Solutions GERAPID 2607, 4207, 6007, 8007 with arc chutes 1X2, 1X4, 2X2, 2X3, 2X4 User Manual
Page 47
2010-06-07 S47183e rev.03
Design and specifications are subject to change without notice
47
Fig. 55-4 Unscrew all the plugs from control boards
Fig. 55-5 Pull out the plugs of the control boards. Pull out
selected control board. Insert new control board
•
Listen that both, the isolation plate at the side of
equipment and the isolation plate at the side of
soldering, were inserted!
Fig. 55-6 Plug in all control plugs and tighten it by the
screws.
Fig. 55-7 Pay attention, that no cables will be pinched
between box and front cover during closing!
Fig. 55-8 Carefully replace the control box front cover and
attach the with the four screws
•
Put on plugs X2…X6, fix the screws of the plugs and
switch on control voltage.
Checking the breaker:
•
Open and Close the breaker 3 times while it is
disconnected from the system (in the “Test-position“ of
the draw out version/the installation). The breaker must
open and close without a time delay over 400 ms.
•
If the test succeeds, reconnect the breaker to the main
circuit.