Rectifier Utility data screen
This screen refers to the AC source supplying the Rectifier.
This screen displays:
• Iout1 = output current Rectifier Bridge.
• Iout2 = output current 2

nd

Rectifier Bridge (optional 12 pulse Rectifiers only).

• The voltage levels between the three phases (line-to-line).
• The input frequency of the Rectifier.

R EC TIFIE R

U 12=481V

Iout1

=61A

U 23=480V

Iout2 = 0A

U 31=482V

f=60.0H z

m etering

alarm s

param eters

+

ok


Inverter data screen
This screen displays:
• The voltage level of the three phase voltages (line-to-neutral).
• The output frequency of the Inverter.
• The synchronization status of the Inverter with respect to Utility.

INVERTER: U1=277V
U2= 277V

U3=277V

Frequency = 60.0Hz

Synchronized

metering

alarms

parameters

+

ok

Status Load screen
This screen displays:
• The Load level in kVA (for RPA: only this unit).
• The Load level as a percentage of the nominal rated Load (for RPA: only this unit).
• The source of the power supplied to the Load.

LOAD ON UPS

Load =

25.20kVA

Percentage = 84%

LOAD ON INVERTER

metering

alarms

parameters

+

ok


Load on phases screen 1
This screen displays for each phase:
• The output phase voltage and current as RMS values (for RPA: total value of Parallel System).
• The output Load as percent (for RPA: respect to the rated power of Parallel System).

LOAD ON PHASES

U1=277V I=30A 84%
U2=277V I=26A 73%
U3=277V I=27A 76%

metering