7 operation, Operation – GE Industrial Solutions SG Series 10 – 20 – 30 – 40 kVA Operating Manual User Manual

Page 42

Advertising
background image

Modifications reserved

Page 42/83

OPM_SGS_USM_10K_40K_0US_V030.doc

Operating Manual SG Series 10 –20 – 30 - 40 kVA

7 OPERATION


This symbol refers to the operations of a parallel system.



NOTE !

Verify for correct input/output cabling before connecting Utility to the
UPS.
Open only the front door, do not remove any panels.

Now you can initiate the start-up procedure of the UPS system.
There is no need for specific knowledge if you follow carefully the step-
by-step instructions given below.
But we recommend, that at least the initial procedure, should be

performed by an instructed person.

Check after every step for correct reaction of the UPS (LED’s on the panel),
and correct voltage and current measurements, before you proceed to
the next step.


If you encounter any problems during the following procedures, you
should not continue, but contact GE Global Services
.



Find on the following pages the descriptions of the various procedures of start-up and
shutdown for single and parallel UPS’s
, divided into the following principal chapters:

7.1

PROCEDURES FOR SINGLE UPS


7.2

PROCEDURES FOR UPS FUNCTIONING AS FREQUENCY CONVERTER


7.3

PROCEDURES FOR PARALLEL SYSTEM


7.4

PROCEDURES FOR PARALLEL SYSTEM WITH COMMON BATTERY

Advertising