7.2.4 Restore to normal operation after EPO (Emergency Power Off)

UPS panel after activation of EPO
(Emergency Power Off)
with Utility
not available, i.e. complete

shutdown of the UPS.
In this case wait until Utility
is
again available, then proceed to
restart the UPS as described
below. Points 1 through 3.


UPS panel after activation of EPO

(Emergency Power Off) with Utility
available
.

All Contacts are open.

Rectifier, Inverter and Static-Switch
shutdown.

1. Reset the EPO (Emergency Power Off)

button.
• Press mute, to reset alarm and buzzer.

2. Press inverter off ( O ) key.

Rectifier starts with blinking LED.
• At the end of Soft-start the LED

remains lit.

The LCD screen shows: “LOAD OFF”.

3. Press inverter on ( I ) key.

Inverter starts with blinking LED.
• At the end of Soft-start the LED

remains lit.

UPS output LED and LCD screen

indicate both: “LOAD ON INVERTER”.

END OF PROCEDURE