7.1.2 Maintenance shutdown (Load on Q2)

Initial status:

Load supplied from Inverter.

1. Press inverter off ( O ) key and hold until

the LED inside the Inverter symbol turns
OFF
.
Load is transferred to Utility.
Inverter shuts down.
LED Inverter must be OFF.

The LCD screen must display the status “LOAD ON BYPASS”.

2. Close Q2 (Pos. I).

Load is now supplied parallel through

Bypass and Q2.

LED for Manual Bypass lights up.

3. Open Q1 (Pos. O) and then press total off

button.
Load is now supplied from Manual Bypass.
Rectifier shuts down and all output and

input contactors are opened.

The LCD panel must display the main screen, indicating the status “LOAD OFF”.

4. Disconnect the Battery from the UPS in case

of External Battery.
• Wait 5 minutes for DC-Link Capacitors

discharge.

END OF PROCEDURE