5.

Restoring the Unit to Operation

a. Turn power on at breaker.

b. Unit should begin to fill. Maximum fill time is approximately 30-45 minutes before

contactor(s) will be closed.

c. Go into the Operation Setup menu and verify that the unit is in “Steam Gen”.

d. See the Unit Configuration menu (Password ARMH) to go to the “EOL (end of life)

Reset”.

This must be done to reset the timer.

6.

Modifying the Bed Life Setting

1. Complete the steps for servicing the unit as outlined above.

2. Change the EOL settings to desired value in Unit Status menu.

3. Save settings in menu.

End of Season Drain

If at any time during normal operation there is not a demand for a continuous 72 hour period,

HumidiClean drains the tank and the PC Board initiates a drying cycle by cycling the heating elements

for short intervals in order to dry the ionic beds.

Replacing the Ionic Beds

1.

Save the settings, consult the OPERATION SETUP menu

2. Go to

Steam Gen. Menu

a. Drain tank by operating menu from “STEAM GEN.” to “MANUAL DRAIN” position.

b. Once the tank is drained, shut power off to unit and allow the tank to cool.

c. Remove the cabinet access panels, and slowly open tank access panel.

3. Unsnap ionic beds from support pins and slide them out through the access opening.

4. Inspect tank drain screen and elements inside the tank. The elements should appear to be flaking

off scale. If the drain screen appears to building deposits in the screen holes it should be cleaned.

Remove any scale that appears in the bottom of the tank.

5. Install six (6) new ionic beds (14 for the HC-6500/6700), snapping them into place on the

support pins. (Pinch ends to secure.)

6. Make sure access panel gasket is lapped over all edges of tank access opening. Replace and

secure tank access panel.