Table 8.1 - Preventive Maintenance Schedule (Continued)

Component

Testing
Interval

Test Procedure

Supervisory
Signal Initiating
Devices

Semi-annually

1. Put zone in test mode
2. Operate valve
3. Test pressure, temperature, and water level sensors per the sprinkler system
test procedure

Remote
Annunciators

Annually

1. Verify all indicators operating properly.
2. Verufy RTU Trouble Signal Operating properly.

Alarm Indicating
Appliances

Annually

1. Visual Inspection
2. Put panel in alarm, drill, or test mode. Verify all indicating appliances operating
properly

All Initiating
Device Circuits
Verified
Non-Verified
Waterflow
Waterflow w/
Retard
Supervisory

Annually

1. Bypass zone and enter test mode
2. Short IDC zone (15 Sec. For waterflow). IACs should activate, sounding the
zone number
3. Wait 15 seconds. Place 1.1K

across IDC. IACs should activate, sounding the

zone number
4. Wait 15 seconds, then open the IDC field wiring. IACs should activate, sounding
a 1 second pulse
5. Wait 15 seconds, then ground one side of the IDC field wiring. IACs should
activate, sounding a 1 second pulse
6. Reset and lock panel at conclusion of all testing

Panel LEDs &
Trouble Buzzer

Annually

1. Illuminate all LEDs by pressing the RESET switch
2. Reset and lock panel at conclusion of all testing

Panel Primary
Power

Acceptance and
Re-acceptance
tests

1. Remove Primary AC power
2. Verify panel operates from battery
3. Verify panel goes into trouble (6 second delay)
4. Restore AC power at end of test
5. Reset and lock panel at conclusion of all testing

Panel Secondary
Power

Acceptance and
Re-acceptance
tests

1. Remove Primary AC power
2. Measure standby and alarm currents, and compare with battery calculations to
verify adequate battery capacity.
3. Test under full load for five (5) minutes
4. Measure battery voltage under full load (20.4 to 27.3 VDC)
5. Restore AC power at end of test
6. Reset and lock panel at conclusion of all testing

Panel Trouble
Signals

Annually

1. Verify operation of System Trouble LED and trouble buzzer
2. Reset and lock panel at conclusion of all testing

Auxiliary System
Off-Premise Fire
Alarm
Signal
Transmission

Monthly

1. Coordinate test with receiving location
2. Verify receipt of all transmitted signals
3. Reset and lock panel at conclusion of all testing

Remote System
Off-Premise
Waterflow
Signal
Transmission

Every 2 Months

1. Coordinate test with receiving location
2. Verify receipt of all transmitted signals
3. Reset and lock panel at conclusion of all testing