Post-repair checklist, Post-repair, Checklist – ADIC SNC 5100 User Manual

Page 99

Advertising
background image

Post-Repair Checklist

91

6-00020-02

SNC 5100

Post-Repair Checklist

It is important that the items in this checklist are verified after you have
completed a repair action. This ensures a successful reinstall of the product.

Table 4-1: Post-Repair Checklist

Step

Actions

Comments and References

1

Reinstall the SNC 5100
in its original location.

See “Replacing the SNC 5100” on page 84

2

Ensure that the FC hosts
are turned off. if not,
disconnect the FC cables
now.

If you cannot turn off the FC hosts you must
disconnect the FC hosts before turning on the SNC
5100. This is a safety precaution that ensures that FC
hosts cannot perform any I/O to the SCSI target
devices prior to restoring the SNC 5100 configuration
in step 8, below.

3

Attach the Service
Terminal to the SNC
5100

None.

4

Turn on the SNC 5100.

None.

5

Wait for the SNC 5100
to finish booting.

Within one minute, the Ready LED should start
flashing once per second and the “Done executing
startup script” message should be displayed on the
service terminal.

If not, go to “Start MAP” on page 42.

6

From the service
terminal, enter the

targets

command.

See “Service Port Command Reference” on page 105.
If all attached SCSI devices are not shown, go to
“Start MAP” on page 42.

7

If you replaced the SNC
5100, configure the
network parameters.

Obtain the network parameters.

Advertising