3.

Pull the shaft (J100) with bearing (J150) out of the
pump. If necessary, tap lightly on the shaft to dislodge it
from the cylinder block. C

4.

Remove the retaining ring (J200) using retaining ring
pliers. Press the bearing off the shaft.

5.

Inspect the shaft journals for wear, scratching, and pits.
Check the splines for fretting; replace if damaged.
Rotate the bearing, if it does not rotate smoothly,
replace it.

6.

Press the bearing (J150) onto the shaft (J100) and
replace the retaining ring (J200). Ensure the retaining
ring diameter is less than 38.84 mm [1.53 in] when
installed on the shaft.

7.

Install the shaft/bearing assembly into the pump.

8.

Lubricate and install a new O-ring (J260) onto seal car-
rier (J275). Press a new seal (J250) into the seal carrier.

Press the seal until it is flush within +0.12mm [0.005 in]
or -0.72 mm [0.0028 in] of the inside lip of the carrier as
shown below.

9.

Cover the shaft with a protective sleeve while installing
the seal carrier. Hand press the seal carrier into the hous-
ing. Ensure the seal carrier clears the spiral ring groove
in the housing. Remove the protective sleeve.

10.

Wind the spiral ring into the housing. Ensure the inside
diameter of the spiral ring is greater than 68 mm [2.677
in] after installation.

Figure 5-38. Shaft assembly