Series 8700 / 8800 Unitized Curtain Wall Installation Instructions

Figure 6

Section 3 - Static Starter Sill Preparation and Installation

2. Verify that all job site conditions and accompanying substrates receiving the installation are in tolerance and are in accordance with the contract documents.
3. Pre-cleaning

the

substrates

where the caulk joints will be applied later may be advisable prior to setting the starter sill. Final cleaning and sealant primer

application where required should be performed only immediately before caulk joint sealant application.

4.

Use established bench marks to ensure the accuracy of the starter sill location. Precise measurements and coordination with regard to established bench
marks are critical to ensure that the starter sills are installed in the correct location. Improperly installed, or miss-located starter sills will cause significant
problems for the remainder of the erection process.

Apply shim between end
dam and condition.

Slide base anchor away
from anchor location.

Apply shims between
starter sill and condition.

Static Starter Sill