Section 8 - setting units at static starter sills – EFCO 8800 Installation Instructions User Manual

Page 32

Advertising
background image

EFCO 2009

Page 32

Series 8700 / 8800 Unitized Curtain Wall Installation Instructions

Section 8 - Setting Units at Static Starter Sills

1. Static starter sills are used with installations that don’t require provisions for vertical movements at the beginning floor of the curtain wall.
2. Units are typically installed from left to right from as seen from the exterior of the building. Install each frame unit in sequence, starting at the left jamb unit.
3. Units are lifted by the splice bars attached at the head of each unit. These bars are also used to align the units when stacked vertically.
4. Ensure the HC07 caulk backer has been inserted into the sill as shown in Figures 62 and 64 on page 31. Note that jamb units will receive HC07 on both

ends of the sill. Subsequent units will require HC07 on the right end only of the unit sill as viewed from the exterior.

5. Lower the jamb unit down into position onto the starter sill. The hook anchors should also be hooked onto the slab anchors. The unit should now be setting

hard on the starter sill. See Figures 66 and 67.

6. Installations utilizing the static starter sill must use a wind load anchor at the first floor above the starter sill as shown in Figures 68 and 69. All consecutive

floor slabs above the wind load anchor will be the typical dead load anchor as shown in “Section 10 - Setting Typical Intermediate Units”.

7. Place a shim pack between the jamb mullion and the condition to prevent the jamb unit from shifting when setting successive units.

Figure 68

Figure 65

Apply shims between the
unit jamb and condition.

Splice Bar

lift point

Full bearing shims

Static Starter Sill

Wind Load Anchor

Figure 69

Figure 66

Figure 67

Jamb Unit

Advertising
This manual is related to the following products: