Series 8700 / 8800 Unitized Curtain Wall Installation Instructions

Section 15 - Deglaze / Re-glaze Procedures - SSG System

1/8” Shim

FM12 Temporary

Glazing Retainer

WNA3 Gasket

1/2” Nominal

Shim

FM12 Temporary

Glazing Retainer

WNA3 Gasket

WNA3 Gasket

1/8” Nominal

Shim

FM12 Temporary
Glazing Retainer

Figure 145

3. When

re-glazing an opening or openings at a captured unit follow these instructions:

a. Carefully insert new setting blocks in the locations as noted in the approved shop drawings.
b. Clean the new glass or panel and set it in place, centered in the opening, setting on the setting blocks. Do not contaminate the sealant contact

surfaces of the glazing during handling. Press the glazing firmly against the spacer gaskets. Avoid sliding the glazing around on the spacers, as this
can force sealant into visible areas seen from the interior.

c. Apply temporary retainers (FM12) with wedge gaskets (WNA3) at 18” on center of the D.L.O. on all four sides of the opening.

Figure 146

Set the glazing in

place, pressing the

glazing firmly against

the spacer gaskets.

Set the glazing in place,
pressing the glazing firmly
against the spacer gaskets.