21. Using an approved solvent or cleaner, clean the sealant contact surfaces of the starter sill of all oils and other contaminants where the splice will

be applied. The sealant manufacturer’s preparation and application instructions should be followed exactly. If sealant primer is required, apply it
per the primer/sealant manufacturer’s instructions.

22. Apply a bed of sealant on the starter sill gutter that will cover the entire area where gutter splice (HC08 or HC09) will be applied. The sealant must go from

the reveal up the engagement leg to the WC19 gasket track. See Figures 35 and 37.

23. Lay the gutter splice into the bed of sealant. Slide the gutter splice up under the WC19 gasket track. See Figure 37. Smooth the splice down onto the

gutter, forcing out all air bubbles.

24. Apply sealant around the perimeter of the gutter splice. Tool the sealant to ensure a watertight seal at the splice. See Figure 36.

Section 4 - Dynamic Starter Sill Preparation and Installation

Slide the gutter splice up

under the gasket track

and tool sealant to

ensure a watertight seal.

Figure 36

Figure 35

Figure 37

Marry the gutter

splice sealant with

the reveal splice

sealant to create a

watertight seal.

Apply sealant around
the entire perimeter of
the gutter splices and
tool to create a
watertight seal.

Apply a bed of sealant that
will cover the areas where
the silicone splice sleeve will
be applied.

Apply the two piece
silicone splice sleeve.