7) Insert 28" long rebar (8 total, included with fire-

place) vertically through the cells, into the holes in

the hearth, adjacent to the rebar and/or all-thread

sticking up from the hearth (Figure 42). Mix approxi-

mately 2 cu. ft. of Ready-Mix Concrete (not included)

and fill all cells in walls and rear of firebox completely

(Figure 41).

Figure 41- Inserting Rebar and adding Ready

Mix Concrete

Fireplace installation

Continued

8) Attach Lower Seismic Straps to rebar closest to

the front as shown in Figure 42.

Add rebar and fill all

cells with concrete mix

Lower Seismic Straps

12 inch

rebar or

all-thread

Figure 42 - Attaching Lower Seismic Straps

9) Install Downdraft Diverter and final row of Side

Walls (Figure 43). All components must be level. Mix

approximately 2 cu. ft. of Ready-Mix Concrete and fill

all cells with Ready Mix Concrete mix.

Downdraft

Diverter

Figure 43 - Attaching Downdraft Diverter and

Side walls

Final Side Walls

Lintel

Lower Rear

Dome

Figure 44 - Attaching Lower Rear Dome and

Lintel

10) Set the Lintel and Lower Rear Dome in place as

shown in Figures 44. Check that all is level. If you

need to make adjustments, use shims. Place one or

more of these shims between the lowest wall com-

ponent and the top surface of the base plate. Once

you are satisfied with the degree of levelness, you

can address any gap that may have occurred with an