8 checklist for completed installation, Checklist for completed installation – Liebert Challenger ITR User Manual

Page 19

Advertising
background image

Installation

13

2.8

Checklist for Completed Installation

___ 1. Unpack and check received material.
___ 2. Proper clearance for service access has been maintained around the equipment.
___ 3. Equipment is level and mounting fasteners are tight.
___ 4. Piping completed to refrigerant or coolant loop (if required). Piping has been leak checked,

evacuated and charged (if required).

___ 5. Check piping within the Liebert Challenger ITR and outside of the unit. Remove potential of

rub-through or chaffing.

___ 6. Condensate pump installed.
___ 7. Drain line connected.
___ 8. Water supply line connected to humidifier (if required).
___ 9. Field provided pan with drain installed under all ceiling mounted fluid condensing units (if

installed).

___ 10. Ducting completed (if applicable).
___ 11. Filter(s) installed.
___ 12. Line voltage to power wiring matches equipment serial tag.
___ 13. Power wiring connections completed between disconnect switch, evaporator and condensing

unit, including earth ground.

___ 14. Power line circuit breakers or fuses have proper ratings for equipment installed.
___ 15. Control wiring connections completed to evaporator and condensing unit.
___ 16. Verify water detection is properly installed around all units (if installed).
___ 17. All wiring connections are tight.
___ 18. Control panel DIP switches set based on customer requirements.
___ 19. Foreign materials have been removed from, in and around all equipment installed (literature,

shipping materials, construction materials, tools, etc.).

___ 20. Fans and blowers rotate freely.
___ 21. Inspect all piping connections for leaks during initial operations. Correct as needed.
___ 22. Verify that a blank start-up sheet has been sent with the unit(s) and is ready to be completed

by the installer.