TEST RUN

„ Before test run

• Before turning on the power supply, carry out the following

procedure.

1) Using 500V-megger, check that resistance of 1M:

or more exists between the terminal block 1 to 3 and
the earth (grounding).
If resistance of less than 1M: is detected, do not run
the unit.

2) Check the valve of the outdoor unit being opened

fully.

• To protect the compressor at activation time, leave power-

ON for 12 hours or more before operating.

„ Execute a test run

Using the wired remote controller, operate the unit as usual.
For the procedure of the operation, refer to the attached
Owner’s Manual.
A forced test run can be executed in the following procedure
even if the operation stops by thermostat-OFF.
In order to prevent a serial operation, the forced test run is
released after 60 minutes have passed and returns to the
usual operation.

CAUTION

• Do not use the forced test run for cases other than the

test run because it applies an excessive load to the
devices.

Procedure

1

Keep

button pushed for 4 seconds or more. [TEST] is

displayed on the display part and the selection of mode in the
test mode is permitted.

Procedure

2

Push

button.

Procedure

3

Using

button, select the operation mode, [Cool] or

[Heat].
• Do not run the air conditioner in a mode other than [Cool]

or [Heat].

• The temperature controlling function does not work during

test run.

• The detection of error is performed as usual.

Procedure

4

After the test run, push

button to stop a test run.

(Display part is same as procedure 1.)

Procedure

5

Push

check button to cancel (release from) the test run

mode.
([TEST] disappears on the display and the status returns to a
normal.)