Installing the motor (not provided), Installing the belts, Assembly – Grain Systems Unload Augers PNEG-1430 User Manual

Page 18

Advertising
background image

4. Assembly

18

PNEG-1430 6"-6", 6"-8", 8"-8", 8"-10" and 10"-12" 25° Bin Unloader

Installing the Motor (Not Provided)

1. Attach the motor to the motor mount plate using appropriate bolts, lock washers and hex nuts.

(See Motor Bolt Chart below.)

2. Install pulley onto motor shaft making sure that it is aligned with the flight pulley. It may be necessary

to move spacers to gain shaft alignment.

(See Figure 4J.)

Figure 4J

Installing the Belts

1. Place the belts on the pulleys.

2. Screw the lower motor mount adjustment nut upward, thereby raising the motor mount plate and

putting tension on the belts.

3. Once the desired tension is reached, tighten the upper motor mount adjustment nut down onto the

motor mount plate to lock it into place.

(See Figure 4K on Page 19.)

Motor Bolt Chart

Motor Size

Hex Bolt Size

Qty

56

5/16"-18 x 1-1/4"

4

143T

145T

182T

3/8"- 16 x 1-1/4"

4

184T

213T

215T

254T

1/2"-13 x 1-3/4"

4

256T

Advertising