4.4.3.2 B

ATTERY

T

EST

NOTE:

The Battery License is required to perform a full battery test.


The battery test starts when:

the time period between two automatic tests is reached (see Comp@s user manual for more details)

OR

the “BATT TEST” button is pressed for a period of more than 5 seconds.


During the test, the green “LVD ON” LED flashes.
The battery test cannot start when:

an alarm is present

the batteries are charging or discharging

the mains is absent

NOTE:

The delay between two tests is set as 180 days. It starts:

after an automatic test

after each manual test

after stopping a manual test

when the MCU is inserted into the shelf

each time the whole system, including the MCU, is switched ON


When the test is started (manually or automatically after 180 days), all installed rectifiers are set to deliver a low

output voltage (lower than the battery voltage). The batteries are discharged at a fixed current which can be set

by the user. The difference between the load current and the battery current is supplied by the rectifiers (the

rectifiers keep the battery discharge current stable in case of load variations during the test). The discharge

current and the battery voltage are measured and integrated. As the battery discharging current is always the

same, the discharge curves from different discharge tests can easily be compared.
The battery test terminates when:

the programmed power (30% to 50% of the nominal battery Ah value) is extracted before the end

voltage (44V or 46V)

the end voltage is reached

OR

the “BATT TEST” button is pressed.

The batteries are discharged until 30% (user settable) of their nominal capacity has been extracted. The nominal

capacity of the batteries is a variable set by the user via Comp@s. The battery test settings can be modified via

the dedicated Comp@s page, as shown in Figure 35 .