4.1.2 Installation component requirements

Supplied

Internal DC cables

Not Supplied

Concrete and metal grating mounting hardware

AC electrical conduit, cable and fittings

External DC conduit, cable and fittings

Auxilary frame (2" x 9/16") for external battery return busbar kit

4.2 Tools and Test Equipment

Insulated tools are essential for a DC power system installation. Use the following list as a guide:

Electric drill with hammer action

Digital voltmeter equipped with test leads

Lap top computer with Internet Explorer 8 for communication with the Cordex Controller (not required for
initial installation and test)

Various crimping tools and dies, to match lugs used in installation

Torque wrench:1/4" drive, 0-150 in-lb for battery post connections

Torque wrench: 3/8" drive, 0-100 ft-lb for system connections

Insulating canvases as required (2' x 2', 1' x 1', 3' x 3', etc.)

Cutters and wire strippers (#14 to #22 AWG) [2.5 – 34 mm

2

]

Insulated hand tools listed below:

Combination

wrenches

Ratchet and socket set

Various

screwdrivers

Electricians

knife

Fine tipped slot screwdriver (“tweaker”)

Cable

cutters

4.3 Floor

Loading

4.3.1 Concrete floors (for reference only)

Concrete floor installation requiring seismic compliance requires approval by the appropriate engineering disci-
pline, i.e., civil, structural etc. The thickness of the concrete should be evaluated to ensure that its weight carrying
capabilities meet the requirements.

Check the building floor plans for the presence of pipes, conduits, beams or any other obstructions in the con-
crete slab that could interfere with the drilling.

Figure 17 shows the dimensions and bolt locations of a single bay. An anchoring kit is provided with hardware for
the slots