Commander LI90 Series

Rev 1_3

o

Select either an Independent Relay #5 and #6 or Duplexing Relays #5 and #6.

Independent

Relay #5 & #6

Duplex

Relay #5 & #6

Alternate

Relay #5 and #6

o

Independent Relays – Relays #5 and #6 perform the same as relays #1 through

#4. The two relays are not linked together.

o

Duplex Relays – Relays #5 and #6 are linked together with two unique start

levels and a common off position. The relays will also alternate between each
LEAD start. If the level ever reaches the LAG start, the remaining relay will
activate.

o

Alternating Relays – Relays #5 and #6 will switch back and forth each time the

ON level is reached. This is used to maintain a common use/life cycle for
equipment.

o

Relay settings must be in the same units used for the Empty and Full settings

1. Relay #5 ON or LEAD ON

2. Relay #5 OFF or ALL OFF

3. Relay #6 ON or LAG ON

4. Relay #6 OFF