Nexo GEO D User Manual

Page 27

Advertising
background image

GEO

D

RIGGING PROCEDURE

Page

27/97

x 4

1

2

5.3 GEO D – GEO SUB Ground Stacked

Stacking a GEO D10 cluster requires the following accessories:

• 1 x GEO D Main Bumper (GEOD-BUMPER)
• 1 x GEO D Bumper Stands kit (GEOD-BUDP)
• 6 x GEOD push-pins per stacked GEO D10 or GEO SUB (BLGEOD)
• or 1 x GEOD shoulder bolts and nuts kit for fixed installations per stacked GEO D (GEOD-

BNFIX)

IMPORTANT

Ensure platform (ground, riser…) is solid enough to support stacked cluster weight
(distributed on four points), and perfectly horizontal.

5.3.1 Allowed stacked configurations

IMPORTANT

Allowed Stacked Configurations are:
- 4 GEO D maximum
- or 1 GEO SUB max (bottom) + 3 GEOD max (top)
- or 2 GEO SUB
Bumper angle must never exceed +/- 6.5°

5.3.2 Installing Bumper Stands on Bumper

• Install bumper stands and nuts according to drawing below.

IMPORTANT

Make sure nuts are properly positioned on both sides of the bumper. These are
mandatory for system safety

• Adjust length of each stand so that desired bumper angle is achieved (bumper side edge angle in

relation to horizontal); ensure that bumper front edge is perfectly horizontal;

• Secure

nuts.

INSTALLING BUMPER STANDS

Advertising