• Insert two additional 10mm x 20mm push-pins in the front holes (see figure above).
• Lift the bumper and two first GEO SUB’s to a height that allows convenient access to the linking

bars and the angle setting holes.

• Insert 1 additonal push-pin to the required angle value hole on each side
• Check that all 6 push-pins are locked.

IMPORTANT

Ensure angle settings are identical on both sides of the cabinet.

5.6.4 Last GEO SUB to First GEO D10

4 push-pins (BLGEOD, 10mm diameter x 20 mm length) connect first to second GEO SUB, 2 additional
push pins-are required for angle adjustment.

LAST GEO SUB TO FIRST GEO D

• Lift bumper and top GEO SUB assembly, and position the next GEO SUB below the assembly,

with NEXO logo on the same side than the upper cabinet.

• Lower bumper and top GEO SUB assembly carefully until the GEO SUB and GEO D10 side

rigging plates locate. Use front grid, rear vent ports or handle to guide the assembly. The rigging
plates have been designed to locate against each other and so align the holes correctly.

• Connect the upper GEO SUB link bar to the lower GEO D10 rigging plate (or lower link bar to

upper rigging plate for “Right” configuration) by inserting one 10mm x 20 mm push-pin in the
“SAFETY PIN MUST BE FITTED” hole on each side (see figure below).

IMPORTANT

The push-pins for “SAFETY PIN MUST BE FITTED” holes must always be inserted first and
stay in position permanently.

• Insert two additional 10mm x 20mm push-pins in the front holes (see figure above).
• Lift the cluster to a height that allows convenient access to the linking bars and the angle setting

holes.

• Insert 1 additonal push-pin to the required angle value hole on each side
• Check that all 6 push-pins are locked.