 3      Installing  the  Air  Locker  

 

 

25

3.11

     

Bench  Testing  the  Air  Locker  

 

F

 To  test  the  Air  Locker;;  when  620kPa  [90  PSI]  shop  air  is  applied  to  

the  seal  housing  tube,  the  Air  Locker  should  engage.  

F

 Check  all  fittings  and  the  seal  housing  for  air  leaks.  

F

 Rotate  the  differential  carrier  by  turning  the  pinion  flange  whilst  

applying  air  pressure.  

 

 NOTE  :      An  accurate  way  to  test  for  air  leaks  is  to  fit  a  shut-­off  

valve  to  an  air  pressure  gauge  (ARB  part  #  0770005).  

Once  620  KPA  [90  PSI]  is  reached  close  the  valve,  
disconnect  the  air  hose,  and  watch  to  see  if  there  is  any  
drop  in  pressure.  If  so,  this  will  indicate  an  air  leak.  
(Fig.15.)
 

 

 Figure  15.  

 
 

 
 
 
 

 
 
 

 
 
 

 

F

 If  a  leak  is  found  to  be  present,  spray  a  soap  and  water  mixture  

onto  the  bulkhead  air  fitting.  Bubbles  should  appear  at  any  leak  
points.    

   

 NOTE  :          Do  not  spray  this  soapy  mixture  inside  the  differential.    

 

F

 Check  that  leaky  fittings  have  been  adequately  tightened.  

F

 Disassemble,  clean  threads,  and  reapply  thread  sealant  if  leaking  

persists.    

If  a  leak  is  found  at  the  seal  housing,  carefully  remove  the  seal  

housing  assembly  and  examine  the  O-­rings.  Be  very  careful  with  the  
O-­rings  and  check  for  defects,  damage,  wear,  or  presence  of  foreign  
material  in  the  O-­ring  grooves.  Replace  if  necessary.  