Commissioning

4.1

Initial switch-on

For commissioning, the system bus must be completely wired.

#

#

#

#

Stop!

Before switching on the supply voltage:

!

Check the wiring for completeness and short circuits,

!

Check whether the bus system is terminated physically at the first and last
station.