SeTUP:

• Before powering or starting, check for damage, that could prevent this equipment from proper

operation or performing its intended function. Check for binding and improper alignment of
moving parts. Check for damaged, broken, or missing parts.

• Verify the On/Off switch is in the OFF position.
• Before connecting the MK-145 to a power supply, be sure the voltage, cycle and phase of the

job site power source meet the requirements of TABLE 3.

• If using an extension power cord, ensure sure the length and wire gauge correspond to the

requirements listed in TABLE 1 on Page 9. An extension power cord that is too small in wire
gauge (diameter), or too long in length, will cause the motor to overheat and could cause
premature failure.

• Use an approved Ground Fault Circuit Interrupter (GFCI).
• Do not cover the motor vents as this could lead to motor overheating.
• Do not overfill the Cooling Basin.

NOTe: In order to avoid breaker tripping, a 15-amp circuit breaker should be used.

CAUTION

Voltage

120V

Cycle

60 Hz

Phase:

1-phase

Table 3

(A)

Place MK-145 on a flat,

level surface and verify the

Diamond Blade is aligned

with the Blade Guard

Support Angle using

straight edge

(B)

Loosen the Blade Guard

Support Screw and align

the Blade Guard to the

Diamond Blade then

retighten the Blade Guard

Support Screw

(C)

Lift Water Basin Cover and

pull out on Water Basin

Cover to remove