f. Locate leg guides on bolts and secure with

nuts.

g. Ensure both cutterbar tie-downs on transporter

are in the down position and the transporter is
cleared of tools or other debris that may
damage the header.

3.11.2 Loading Procedure

a. Disengage header lift cylinder stops and start

combine.

b. Approach transporter from left hand side, lining

up the mid-point of the header (center-link)
with the mid-point of the two center supports
on the transporter.

NOTE

Orange or red marking tape on the
transporter frame identifies the mid-point
between the center cutterbar supports.
Tape may need to be relocated
depending on header configuration.

Refer to SECTION UA. Step 2.
Configuring the Transporter.

TIP

Mark the center guard with fluorescent
paint/marker or equivalent to assist in
lining up header with transporter. The
center guard is at the mid-point of the
header opening.

c. Slowly continue forward until the guards touch

the white plastic stops on the transporter.
Lower header as required so that the white
plastic stops remain visible from the operator’s
station.

(continued next page)