Rockwell Automation Publication 7703E-IN001E-EN-P - July 2014
Chapter 7
Final Test Procedures
Start-Up
1. Remove any temporary jumpers or grounding devices used during
commissioning.
2. Check that all tools are removed from the equipment. Any tools or
hardware used or dropped during installation and commissioning must be
retrieved and accounted for.
3. Check that all barriers or covers removed during installation or
commissioning have been securely mounted.
4. Close and secure all doors, and verify function of all interlocks that
prevent access to medium voltage compartments when the unit is
energized.
5. The controller is ready to power the motor.
Spare Parts
For a complete listing of spare parts, refer to