Pak 200i – Tweco PAK 200i User Manual

Page 29

Advertising
background image

PAK 200i

Manual 0-5335

INSTALLATION

3-5

Connect Input Power and System Ground Cables for 400V CE systems

1. Remove the input power cover to the right of the coolant filter at the rear of the power supply. To do this

remove the two screws then lift up and pull away.

2. Carefully cut back the outer sheath on the primary input power cable to expose the individual wires. Cut

back the insulation on the individual wires. Route the cable upward through Input Power Port at the bottom

of the panel. There are 2 extra plates included at the cable entrance. Discarding one or both allows changing

the opening size for larger cable/strain relief.

J15 - CNC

CB4 - 5A 120 VAC

F1 - 8A SB 230 VAC

F2 - 8A SB 230 VAC

CB3 - 5A 24 VAC

CB2 - 5A 120 VAC

USER INPUT

HEIGHT CONTROL

AIR / O2

PLASMA

N2 / H35

PLASMA

Input Power

Art # A-11949

3. Install stripped end of 3 phase wires into the terminal block L1, L� and L3 and connect the individual cables

as shown.

Advertising