Flow Adjust: Hydraulic Drive Center-Fill
IntelliAg

®

Air-Pro

®

Planters

On hydraulic drive models YP1225A#56, YP1625A#56,
YP2425A, YP3025A/AR, YP4025A/AR, YP4425A and
3PYPA#56, the PT
O system drives two

a

motors,

plumbed in parallel:

a.

The fan motor generates an airflow for seed delivery
and meter pressurization. The ratio is servo vane
controlled by the DICKEY-john

®

IntelliAg

®

seed

monitor. The vane needs to be active for accurate
flow control adjustments.

b.

The seed meter shaft motor is under seed monitor
control, via a proportional flow solenoid valve. When
engaged at typical seed rates, operating this motor
reduces flow to the fan motor. The seed motor needs
to be engaged at least briefly during setup to choose
a flow rate that keeps the fan at optimal speed.

Adjustment Steps:
1.

Have the DICKEY-john

®

Planter/Drill Control User

Level 2&3 manual at hand. Making changes to the
GROUND SPEED SETUP configuration requires
the Level 2 password.

2.

Have the Operator and Seed Rate manuals at hand,
so that meter setting and fan rpm targets are known
for the seed to be planted.

3.

Loading seed is not required. If you do load seed,
set out recovery means to capture seed metered
during testing, or use section clutches

b

to disable

metering.

4.

Turn the IntelliAg

®

monitor system on.

Turn the Master switch off.
On the console, navigate to the
GROUND SPEED SETUP screen.
Record the ground speed constant:

5.

Set:

6.

Hitch the tractor to be used, and install the PTO
pump. Raise the planter. Unfold the planter.

Refer to Figure 9
7.

Release the lock disc

counter-clockwise to

release the knob

. Turn the knob fully clockwise to

shut off flow to the motors.

Entanglement and Crushing Hazard:
Use extreme caution in the hitch area when the PTO is
operating.

8.

Start the tractor, and seed monitor. Bring the PTO
up to expected field rpm (which is often not the full
1000 rpm).

9.

Turn the IntelliAg

®

Master switch on to engage the

hydraulic seed meter drive.

10. With one person observing the fan rpm readout on

the seed monitor, turn the knob
counter-clockwise until the fan is at the rpm
recommended for this planter configuration, crop,
population and intended field speed.

Secure the knob at this setting with the lock disc.

11. Shut down the PTO. Set Master switch off.

12. On the console, navigate to the

GROUND SPEED SETUP screen.
Restore the original settings:

Monitor fan rpm when planting. If it is lower than during
flow setup, perform the setup steps again, and set the
valve for a higher rpm.

a. When the Yield-Pro

®

PTO pump system was installed, there was an option to use it only for the air system, and leave the hydraulic

drive on a dedicated tractor connection. In this case, load seed, but ignore the steps to compensate for seed drive motor load.

Figure 9:

Flow Control Valve (3PYPA#56)

34848

81

8-240C Re

v. A

To a

void Injur

y or

Mac

hine Dama

ge:

·Operate onl

y with

1000 rpm PT

O

CAUTION

858-030C

All dr

iveline guards

, tr

actor

an

d equip

ment shields in p

lace

PT

O pump assemb

ly securely

attached with torque ar

m and clamp

bolts proper

ly torqued

RO

TATING DRIVELINE -

CONT

ACT CAN CA

USE DEA

TH

KEEP A

W

AY!

DO NO

T OPERA

TE

WITHOUT

-

DANGER

1

2

b. If Swath Command™ section control is installed, connect the compressor at the hitch, or clutches will not disengage.

Source
Gspd Constant

Digital Freq.
12345

(actual value varies)

Source
Manual Gnd Spd
Implement Lift

Manual
5.0 MPH

(or as desired)

Disabled

1

2

Source
Gspd Constant
Implement Lift

Digital Freq.
12345

(actual value varies)

Enabled

2

Advertising