Meter Slide Maintenance
(Singulator Plus meters only)

For proper seeding operation, seasonally or when
changing crops, check meter slide for wear. If you have
a noticeable increase in seeding rate you may need to
replace the meter slide.

1.

If seed box is not empty, shut off sliding seed tubes.
See “Row Unit Shutoff” on page 32.

2.

Clean out seed meter. See “Cleaning Out Meters
on page 63.

3.

Remove wheel. See “Seed Meter Setup and
Adjustment
” on page 39.

Refer to Figure 83
The slide

is located at the front of the meter (left side

on 20 Series depicted; right side on 25 Series).

4.

Check for excess wear on meter slide

. Slight

wear at the top corner is normal.

5.

If slide is not excessively worn, stop here. If it is,
continue with step 6 to replace.

Replacing Meter Slide

Refer to Figure 84
6.

Remove retaining clip and pin

from meter.

Note: Meter slide

is spring loaded. Two meter slide

springs

will be released when you pull the pin,

and a third

when you tilt it back. Use care not to

lose pins and springs.

7.

Check removed pin

for wear and replace if worn.

8.

Place springs in new meter slide. Insert in meter
and pin in place.

9.

Re-install meter wheel (page 40).

10. Close and pin meter clean-out (page 63).

11. Re-open seed tube sliding gate if closed (page 32).

Figure 83

Singulator Meter Slide

18269

1

1

1

Figure 84

Meter Slide Replacement

26220

3

4

5

2

2

3

4

5

2

Advertising
This manual is related to the following products: