Section 21 - Unit Glazing Preparation - Vent at Stack Sill

Figure 65

Apply gaskets

flush with the side

of the mullions.

Isolator
Reglet

Insert a 3/8” backer rod into isolator reglets to

keep free of sealant. Remove the backer rod

immediately, before sealant begins to skin over.

Figure 24

Figure 25

4. Apply the WC18 spacer gasket to the mullions as shown below and on the previous page. The gaskets will run through as shown below. Butt the gaskets

together at the corners (see Figure 26). “Crowd” in extra gasket, (approximately 4% to 5% extra) where it runs between the gaskets to ensure a snug butt
joint at the corners. It is important that there are no gaps in the gaskets where they meet in the corners. Note that the gasket is not symmetrical, and must
be installed so that it is flush with the side of the mullions (see Figure 24).

5. A 3/8” backer rod should be applied into the isolator reglet to prevent sealant from getting into the reglet. Remove the backer rod immediately after the

sealant is applied, and before the sealant begins to cure or skin over (See Figure 25).

INTERMEDIATE

HEAD

Butt gaskets at D.L.O.

corners (vertical

gasket runs through).

JAMB

JAMB

Figure 26

Butt gaskets at D.L.O.

corners (vertical

gasket runs through).

INTERMEDIATE

JAMB

Butt gaskets at D.L.O.
corners (vertical
gasket runs through).