Section 23 - SSG Vent Unit Glazing at Stack

Sill

: B. Setting and Caulking Glazing

Figure 43

3. Remove the temporary glazing retainers.
4. Apply structural silicone sealant into the voids between the glass and mullions per the sealant manufacturer’s application instructions. Frames should not be

moved until the sealant has cured and per the sealant manufacturer’s recommendations.

5. Refer to Volume 2, page 9 and 10 of the S-8000 Unitized Curtain Wall Assembly Instructions for glazing instructions, details and notes.

Note:
Only silicone sealants which
have been developed and tested
specifically for structural
glazing applications should be
used for glazing purposes.

Apply Structural

silicone.

Pack sealant

into joints.

HEAD

SILL

Apply structural silicone
sealant into the voids between
the glass and mullions.

Apply structural silicone
sealant into the voids between
the glass and mullions.

Concealed Vent

opening

Advertising